Skip to main content

Current Project Updates

Engineering & Construction Update 

 

Water Treatment Plant Effluent Pumping and Controls

This project is currently moving towards 75 % design. Design expected to reach 75 % in July. A public meeting for the project will be held on August 13th  Board of Director's meeting.

Colorado River Transmission Main Crossing

The trail is expected to close again on the week of June 29th. Construction crews are expected to begin work again on the water main crossing the river. Work is expected to last 2-3 weeks.

Desert Road Pump Station

Design is complete and the District is now finalizing easements for the new site. Bidding for construction is expected to begin in July.

Reeder Mesa Fill Station

Fill station is now open!

Join our mailing list